DOH demolishes northbound span of South Fairmont West Virginia Arch Bridge as part of I-79 widening project

Community Bulletin

The Healthy Hero Hustle 5K Run/Walk in Buckhannon will return for its third year on Saturday, September 19, 2026, as WVU Medicine St. Joseph's Hospital and West Virginia Wesleyan College team up again to benefit nursing students. Read more →

This story brought to you paywall-free, courtesy of the My Buckhannon team and our community partners

CHARLESTON – On Friday, December 8, 2023, contractors for the West Virginia Division of Highways (WVDOH) used explosives to demolish the northbound span of the South Fairmont West Virginia Arch Bridge on Interstate 79. The demolition is part of a massive project to widen I-79 to six lanes from Harrison County almost to the Pennsylvania state line.

Pennsylvania-based Swank Construction was awarded a contract for $72.5 million for the widening project, which included construction of a new six-lane bridge in place of the two South Fairmont West Virginia Arch Bridges that carry I-79 over the Tygart River near the White Hall exit. The southbound span of the old bridge was demolished in March 2023.

Contractors set up a rolling roadblock to set off explosives on the other span at about 10 a.m. Only authorized personnel were allowed within the explosives loading/handling area. Public viewing was not allowed due to safety concerns. Marion County Route 60, Vinegar Hill Road, was closed throughout the week in preparation for demolition of the bridge.

The new I-79 bridge over the Tygart river is about half complete. Contractors first built one quarter of the new southbound bridge before demolishing the old southbound span, then built the second quarter.

St. Joseph's Hospital

Now that the old northbound bridge has been demolished, the northbound half of the new bridge can be built. The widening project is expected to be complete by the summer of 2025.